Update 3 - Summer 2017 Apartments Carpet Replacement

05/28/17

The crew will be starting in Building 5 to remove and replace carpet on Wednesday, May 31. They will start on the first (1st) floor at the earliest on Wednesday. This building should complete within one week (by June 7).

When your unit is next, you will need to do the following things:

  1. Pack a bag and bedding for no more than 3 days/2 nights. We will house you in another open residence hall until the work is completed in your unit. If you would like to make other arrangements for this duration of time, you are welcome to do so.
  2. Box up your belongings and move them to the bathroom’s TILED surface or in your room’s closet while still being able to shut the doors. (Closet carpet will be replaced at a later date.)
  3. Do not leave valuables in drawers (clothes and desk items are okay to be left) as crews will be removing the desk, desk chairs, and drawers. This furniture will be placed in the vanity areas.
  4. Wall decorations may be left on the walls as long as they are above 5 feet from the floor.

The crews are still working in Building 6 & 7. There is still construction clean up and individual unit/bedroom projects (painting, cleaning, appliance work) to be done.

Please be aware of the crews and their location as your unit will be coming up soon. We will keep in contact with you, via email and our main website, about their progress so that you may prepare your things.

Update 2 - Summer 2017 Apartments Carpet Replacement

05/23/17

The crew will be starting in Building 6 to remove and replace carpet on Wednesday, May 24. At this point, we are unable to give you a room order. What we can say is that it will start on the first (1st) floor at the earliest on Wednesday, but for sure on Thursday. This building should complete by the end of the month (May 31).

The crews may still working in Building 7 after Wednesday, May 24. There is still construction clean up and individual unit/bedroom projects (painting, cleaning, appliance work) to be done.

When your unit is next, you will need to do the following things:

  1. Pack a bag and bedding for no more than 3 days/2 nights. We will house you in another open residence hall until the work is completed in your unit. If you would like to make other arrangements for this duration of time, you are welcome to do so.
  2. Box up your belongings and move them to the bathroom’s TILED surface or in your room’s closet while still being able to shut the doors. (Closet carpet will be replaced at a later date.)
  3. Do not leave valuables in drawers (clothes and desk items are okay to be left) as crews will be removing the desk, desk chairs, and drawers. This furniture will be placed in the vanity areas.
  4. Wall decorations may be left on the walls as long as they are above 5 feet from the floor.

Please be aware of the crews and their location as your unit will be coming up soon. We will keep in contact with you, via email and our main website, about their progress so that you may prepare your things.

Update 1 - Summer 2017 Apartments Carpet Replacement

05/18/17

The crew, once finished with the empty apartments, has changed their course of action and has continued in Building 7, as opposed to restarting in Building 5.

The rooms to be started and completed from Monday, May 22 to Wednesday, May 24 are:

7201 – All units

7202 – All units

7208 – All units

7209 – All units

7211 – All units

7214 – All units

7301 – All units

7302 – All units

7303 – A & B

7304 – A & B

7308 – All units

7309 - D

7310 – All units

7311 – All units

7314 – All units

7315 – All units

If your 2 Bedroom unit in Building 7 was skipped, we will be developing a tighter schedule to complete these soon. If your unit is ready, you may notify the main office and we will follow up.

Building 6, 1st Floor will be next on Thursday, May 25.

Please be aware of the crews and their location as your unit will be coming up soon. We will keep in contact with you, via email and our main website, about their progress so that you may prepare your things.

Summer 2017 Apartments Carpet Replacement and Instructions

05/11/17

Over the Spring 2017 semester, our office has been made aware of the need and has made plans to replace the carpet in every Bayou Village Apartment unit.

This project will be accomplished over Summer 2017, starting with those bedrooms and living areas that are completely empty. After that we will be moving to the occupied units starting in Building 5, door to door, then Building 6, and then Building 7.

If you have a 12 month contract or added the Summer Add-on fee, please be aware of the crews and their location as your unit will be coming up soon. We will keep in contact with you, via email and our main website, about their progress so that you may prepare your things.

When your unit is next, you will need to do the following things:

  1. Pack a bag for no more than 3 days/2 nights. We will house you in another open residence hall until the work is completed in your unit. If you would like to make other arrangements for this duration of time, you are welcome to do so.
  2. Box up your belongings and move them to the kitchen’s tiled surface or in your room’s closet while still being able to shut the doors. (Closet carpet will be replaced at a later date.)
  3. Do not leave items in drawers as crews will be removing the desk, desk chairs, drawers, and bed. This furniture will be placed in the bathroom and vanity areas.
  4. Wall decorations may be left on the walls as long as they are above 5 feet from the floor.

Should you have any questions, please contact our office at the information below.


©